Tuesday, March 31, 2020

Advanced Disposal Landfill Citizen Complaint

Please accept the following complaint on behalf of Hurricane Creekkeeper and Friends of Hurricane Creek concerning Advanced Disposal Landfill, Eagle Bluff, (ADLF).

Land permit# 63-26, Water division permit # ALG160090.
Both divisions have received my complaint of Feb. 26, 2020. In that complaint I proved that the so-called tire-wash was NOT being used. On Jan. 23, 2020 the engineering firm Hodges, Harbin,Newberry & Tribble submitted documentation that stated the tire-wash was operational and in service as of January. This is a false statement. The “birdbath” tire-washing basin might have been complete but it was not put in service until the week of March 8th, after channel 33/40 showed up with camera crews. Brian Pia was told when he interviewed Mr. Rogers on or about that day that he had activated the truck wash on Monday after the film crew was there. Either HHNT was mistaken or the landfill intentionally circumvented the consent order by not using it. That comes to at least 68 days of willful non-compliance with a consent order and the permit requirement to contain the mud onsite. Here’s a link to the story Brian ran on the subject. He said he’d be happy to speak with ADEM and in fact already has.
Over a time period starting on 03/11/20, just after the 33/40 story ran until this complaint 03/31/20, I have been monitoring the progress after rain events. I am not impressed.
The ADLF described “Birdbath” tire wash is a complete joke and waste of their money. It works to a very small degree but not well enough to keep the trash and mud paste from being tracked out of the landfill onto 12th street.
Usually the mornings are cleaner since the mud spreader goes about sweeping the previous days mud onto the right of way and onto private property. In some cases he sweeps mud and rocks directly onto people’s graves. Within 2 hours after opening and after a rain, it looks like it did before the birdbath. I like that term. Maybe they can get the buzzards to use it.
One of the major problems they keep facing is the muddy haul road. Sat. of last week they spread some rock down the center of the road but did not spread it. What a waste of money. After a ¾ inch rain it was no use at all. Trucks simply ground it together with mud and tracked it out. The entire road needs a deep layer of rock and replenished more often. That is expensive but as Mr. Rogers told 33/40, “That’s just some of the stuff with running a landfill”. His statement says to me that he knows he can’t control it. Maybe he is part of the problem.
Neither I nor any of the community impacted care about their costs. Our health and safety are more important. This is not just mud. It comes off the tires and undercarriages of trucks, which go into the waste to dump, spin their tires in wet conditions. That packs the trash and mud between the tires and coats the undercarriages. If it is too expensive to operate within the permit parameters they could move on. This facility has completely outgrown its footprint in our community.
Every day they sweep more and more mud onto the right of way that should be contained within their boundary. What is running from the roadside through the intentionally dug ditches to Hurricane Creek is strictly prohibited. ADEM is fully aware of the situation with complaints and news interviews about it lately yet I don’t find any recent files in the records indicating any action has been taken. ADEM P.R. people told Brian Pia, 33/40 News that an investigation would be ordered. I understand the new threat from Covid-19 and the need for social distance but ADEM inspectors can come sit in the cemetery, as I do and observe all they need to see with no human contact.
On 03/23/20 I documented an ADLF employee intentionally digging a trench to drain the mud and water off of 12th street before operating the mud spreader. The tributary that it leads directly to is an unnamed trib to Hurricane Creek, which passes through a small private pond. The sediment stops at the pond but the turbid water passes through to Hurricane Creek, TMDL listed for turbidity. Today’s turbidity reading at HC was 067 NTU downstream and 013 NTU upstream. That is barely a violation elevation but it a clear indicator that whatever they have done, regardless of cost, it is not enough.
What is going on now has been continuous since the increase in traffic was approved by ADEM and our County Commission. It is time to rethink that decision and or 1. Reduce their traffic again to 1,000 Yds. daily, 2. Issue a cease and desist until this can be adequately remedied, 3. Enforce the consent order and permit requirements by penalizing this facility to the maximum extent allowable.
In another message to ADEM, dated 03/11/20 from Michael B. Stowe, he stated he would replay to my Feb complaint within a week. It is now 20 days since that email but it is not in the E-file. I’d like to see it as soon as it arrives. Should be interesting. I have submitted hard evidence of my claims. 33/40 has also documented some of it and the record is full of violations at this facility.  
John L. Wathen,
Hurricane Creekkeeper
Friends of Hurricane Creek

Creekkeeper is a member of
Waterkeeper Alliance
www.waterkeeper.org

Who has the authority to say someone else
 is not being a good steward of the environment?































Thursday, January 9, 2020

Friends of Hurricane Creek Annual Meeting

Friends of Hurricane Creek Annual Meeting

 and Pot Luck Dinner


It's time once again for the Friends of Hurricane Creek annual membership meeting and pot-luck dinner. This event is open to the public and all comers are welcome to bring guests. This is a family event and no alcohol served.

This year we have a special treat. Our long standing board member, Nancy Callahan will be there to sign her new book "Hurricane Creek,(Personal Accounts and Collected Lore)" It a fabulous book of stories and anecdotes of people who once lived and still do live in the Hurricane Creek watershed. Community members who have fond family memories of youth, found and lost within the banks of our beloved creek. There will be a limited number of books available for sale at the event. You can purchase your own at Ernest & Hadley Bookseller, 1928 7th Street, Tuscaloosa, AL.  $30
Hurricane Creek:  Personal Accounts & Collected Lore by Nancy Callahan now available
This book takes you into the living rooms of elders who share stories of their elders raising them in the creek. I strongly recommend this to anyone interested in the real stories of the rich history of Hurricane Creek and the work that has been done to keep it alive and Running Free, Full of Life.

The event starts at 6:30 PM, Jan, 14 and Canterbury Chapel Episcopal Church and Student Center. Follow the link to a map and directions to the church.


From 6:30 to about 7 we have a meet and greet with dinner served at that time. After a few announcements and presentations, I as Creekkeeper, I will give my brief annual report to the members and guests.





There's no better way to express your love and concerns for Hurricane Creek than to come out, meet and support the only group in existence with the sole mission of preserving and protecting our
Crown Jewel,
Hurricane Creek









Sunday, November 3, 2019

Covered Bridge Road complaint


To ADEM;

Please accept the following complaint of behalf of Friends of Hurricane Creek and Hurricane Creek concerning an unnamed polluter on Co. road 59, 33°11'26.05"N    87°17'50.86"W Next to the shell station located at the “Brookwood exit”. It is located in a headwater, unnamed tributary to Little Hurricane Creek, under TMDL.

A large excavation located behind the Shell looks like it’s been in operation for some time now. There is no NPDES permit posted at the entrance and No BMPs except a few bare minimum, Home Depot type silt fences. This was reported to ADEM in July 2019 with no response or corrective action. ADEM has an obligation to insure sites like this one are permitted and comply with the conditions of said permit. So far this is a total failure by the developer and ADEM.

If there is a permit number registered for this site, I respectfully request ADEM forward me the number and take action up to and including, monetary penalty in an amount that reflects at minimum, 103 days of non-compliance that I have documented. This is to see that this site comes into complete compliance and pays the price for operating out of compliance with CWA regs. as well as well as all unpermitted activity.

In mid July I noticed the site was open and no permit placard to indicate the permit # or any registration at all. BMPs at that time were minimal and certainly not adequate to control such a large site. (Photo 02 and 2 a reflect the issues and time frame)

Photo 03 shows no BMPs as well as an unprotected fuel cell along with several discarded oil / hydraulic buckets that remain today.

Photo 04 shows a small section of inadequate Home depot type silt fences, which on 10/21/19 were failing to control the runoff. From this location the storm water leaves by way of a woodland behind the Shell truck stop next door. It enters a drainpipe there where it flows under the parking lot where it enters storm drains under the interstate. The receiving stream below I-59 is an unnamed tributary to Little Hurricane Creek, which is included in the Hurricane Creek T.M.D.L.

Photo 05 shows a complete lack of proper BMPs and a set of silt fences standing under water that makes no sense at all. Storm water from here travels across the site to the area where it enters the drain leading to I-59. Via the Shell parking lot.

Photo 6 shows the improperly stored fuel cell and discarded buckets still remaining.

Photo 07 shows the drainage area as of 11/02/19 and deep rills, silt fences under the mud, and offsite runoff to the Shell drain to Little Hurricane Creek trib.

Photo 08 shows the path of sediment leading away from the unpermitted site to where it enters the trib to Little Hurricane Creek.

Photos 09 -014 show the drainage downstream of the Shell and where it is leaving large sediment deposits as far as 2,000 feet downstream where I sampled.

This site is in chronic disrepair and depositing large amounts of sediment and turbid water and has been for months. It has been reported to ADEM previously but seems to have seen no enforcement action since. Please do your job and go out there and cite this developer. The lack of compliance by the developer is not surprising since ADEM doesn’t seem to take storm water issues seriously, which is absolutely inexcusable.

As of today, 11/03/19 there is no NPDES signage posted. If there is a permit for the site, please forward the permit # as previously requested and be sure there is a CBMPP attached or included. The very act of not posting the sigs is a violation, which needs to be addressed throughout the watershed.